Materiały konferencyjne SEP 2018

— Integrated Mine Operations in practice February 21, 2018 | Slide 12 • Tested and evaluated on a weekly and daily schedule by mine operator • Perform better than manual – typically 10% more blastings per week • Identificiation of activity bottlenecks – in this site is the bolting machine the constraint • Almost 100% utilization of constraint achieved • Buffers used more effeciently – gives a more robust production • Replanning done in seconds instead of hrs Tune the schedule engine to fulfill the mine requirements